Our [http://groups.google.com/group/xotoaster/browse_thread/thread/f9b9898056f6949d approval] included an estimated schedule. This page is to be updated as progress is completed and the schedule changes. | Our [http://groups.google.com/group/xotoaster/browse_thread/thread/f9b9898056f6949d approval] included an estimated schedule. This page is to be updated as progress is completed and the schedule changes. | ||
* Begin - Approval April 18, 2010 | * Current Schedule | ||
** Update - June 7, 2010 - Meeting with Alex, Sameer and Grant | ** Begin - Approval April 18, 2010 | ||
** Update - June 11, 2010 - minimum Activity installs and runs | *** Update - June 7, 2010 - Meeting with Alex, Sameer and Grant | ||
* Month 3, July 18, 2010 - produce a minimum UI to replicate command line features for CD burning and baseline USB Stick functionality | *** Update - June 11, 2010 - minimum Activity installs and runs | ||
* Month 5, Sept 18, 2010 - Test, test, test, adapt to different XO images. | ** Month 6 - [http://www.olpcsf.org/CommunitySummit2010/ Community Summit 2010] | ||
* Month 6, Oct 18, 2010 - Announce and gather further feedback. | |||
* Month 9, Jan 18, 2011 - collect feedback and incorporate into bug fixes and new feature plans. | |||
* Month 12, Aptil 18, 2011 - support, gather feedback, develop & fix, iterate. | |||
* Original Schedule | |||
** Begin - Approval April 18, 2010 | |||
** Month 3, July 18, 2010 - produce a minimum UI to replicate command line features for CD burning and baseline USB Stick functionality | |||
** Month 5, Sept 18, 2010 - Test, test, test, adapt to different XO images. | |||
** Month 6, Oct 18, 2010 - Announce and gather further feedback. | |||
** Month 9, Jan 18, 2011 - collect feedback and incorporate into bug fixes and new feature plans. | |||
** Month 12, Aptil 18, 2011 - support, gather feedback, develop & fix, iterate. | |||