'''Milestone 1''' | '''Milestone 1''' | ||
'''May 24 - May 31''' | |||
'''May 24 - May 31 : ''' | |||
Work on connection manager to provide : Unicast, Broadcast, Multicast of messages and also to make the activity shareable. | Work on connection manager to provide : Unicast, Broadcast, Multicast of messages and also to make the activity shareable. | ||
'''June 1 - June 9''' | '''June 1 - June 9 : ''' | ||
Work on the viewer to enable display of question/slides, facility to mark/type answers/comments according to the UI Specs generated in the Community Bonding period. | Work on the viewer to enable display of question/slides, facility to mark/type answers/comments according to the UI Specs generated in the Community Bonding period. | ||
'''June 9 - June 12''' | '''June 9 - June 12 : ''' | ||
Make an AnswerSheetCollector and Marker Module. | Make an AnswerSheetCollector and Marker Module. | ||
'''June 12 - June 18''' | '''June 12 - June 18 : ''' | ||
Testing and feedback cycle for MileStone 1 | Testing and feedback cycle for MileStone 1 | ||
'''Milestone 2''' | '''Milestone 2''' | ||
'''June 19 - June 25''' | |||
'''June 19 - June 25 : ''' | |||
Make the interface for Demo Mode at the controller side. The Demo Mode should work seamlessly by June 25. | Make the interface for Demo Mode at the controller side. The Demo Mode should work seamlessly by June 25. | ||
'''June 26 - July 6''' | '''June 26 - July 6 : ''' | ||
Make the Editor for making Questions/Slides. | Make the Editor for making Questions/Slides. | ||
'''July 6 - July 12''' | '''July 6 - July 12 : ''' | ||
Provide a way to overlay comments/answers over original questions/slides. | Provide a way to overlay comments/answers over original questions/slides. | ||
'''July 13''' | '''July 13 : ''' | ||
Fill up mid-term evaluation. | Fill up mid-term evaluation. | ||
'''July 13 - July 20''' | '''July 13 - July 20 : ''' | ||
Testing and Feedback cycle for MileStone 2 | Testing and Feedback cycle for MileStone 2 | ||
'''Milestone 3''' | '''Milestone 3''' | ||
'''July 21 - July 28''' | |||
'''July 21 - July 28 : ''' | |||
Work on making a database for questions and answers to be put up on a school server. | Work on making a database for questions and answers to be put up on a school server. | ||
'''July 29 - August 5''' | '''July 29 - August 5 : ''' | ||
Work on documentation and provide a nice website for the activity where people can put up questions and answers. | Work on documentation and provide a nice website for the activity where people can put up questions and answers. | ||
'''August 5 - August 10''' | '''August 5 - August 10 : ''' | ||
Port the activity on Windows also. | Port the activity on Windows also. | ||
'''August 10 - August 17''' | '''August 10 - August 17 : ''' | ||
Internal Alpha release cycle. | Internal Alpha release cycle. | ||
'''August 17 - August 23''' | '''August 17 - August 23 : ''' | ||
Feedback incorporation. | Feedback incorporation. | ||
'''August 24''' | '''August 24 : ''' | ||
Final Evaluation | Final Evaluation | ||
'''August 25 - later''' | '''August 25 - later : ''' | ||
Alpha Release. This will be for a period of 1 month. After this a beta release of a period of 2 months. After this I will try to push it to be a part of the official distributed activties in Sugar. | Alpha Release. This will be for a period of 1 month. After this a beta release of a period of 2 months. After this I will try to push it to be a part of the official distributed activties in Sugar. | ||
---- | ---- | ||