== Vision == | |||
Create a users manual for Sugar. | |||
== Road Map == | |||
Below is a rough draft of a project schedule. | |||
*Week 1 - Target Date July 13. Define scope of document. Assign volunteers to specific tasks. | |||
*Week 3 - Target Date July 27. Deadline for outlines of chapters to be worked on at sprint. | |||
*Week 5 - Target Date Aug 17. Conduct sprint. | |||
The rest is based on the chosen release date for the spring release of Sugar. | |||
*Week 0 - Release Final documentation | |||
*Week -1 Final translation tarballs due | |||
*Week -4 Documentation freeze | |||
*Week -5 Book Sprint II | |||
... | |||
Any experienced release manager ready to flesh this out Roadmap. | |||