|24th April to 9th May | |24th April to 9th May | ||
| | | | ||
* Community bonding period. Gain consensus of the community on the designs and UI of the proposed features. | * Community bonding period. | ||
* Gain consensus of the community on the designs and UI of the proposed features. | |||
* Understand the working of Sugar codebase ( I already have some handson experience with Sugar) | * Understand the working of Sugar codebase ( I already have some handson experience with Sugar) | ||
* Discuss the specifications of all the features proposed with Mr.Tony Anderson and other community members. | * Discuss the specifications of all the features proposed with Mr.Tony Anderson and other community members. | ||
| Line 169: | Line 170: | ||
|31 May to 1st June | |31 May to 1st June | ||
|Send in patches to be reviewed by community. | |Send in patches to be reviewed by community. | ||
Make necessary changes as per suggestions by the mentor. | |||
|- | |- | ||
|2nd June to 15th June | |2nd June to 15th June | ||
| Line 178: | Line 179: | ||
|16th June to 17th June | |16th June to 17th June | ||
|Send in patches for review by the mentor. | |Send in patches for review by the mentor. | ||
Make necessary modifications to the patches. | |||
|- | |- | ||
|18th June to 24th June | |18th June to 24th June | ||
Discuss the backend working of the feature with mentor. | |||
Design the layout for the user interface modications. | |||
Start working on activity resume feature. | |||
|- | |- | ||
|25th June to 26th June | |25th June to 26th June | ||
|Prepare for midterm evaluation. | |Prepare for midterm evaluation. | ||
Re-evaluate the submitted patches and update the documentations. | |||
'Save As' alert and Screenshot alert would be implemented by the midterm evaluation. | |||
|- | |- | ||
|27th June to 28th June | |27th June to 28th June | ||
| Line 199: | Line 200: | ||
|6th July to 15th July | |6th July to 15th July | ||
|Continue with the work on 'Activity resume' feature. | |Continue with the work on 'Activity resume' feature. | ||
Work on the home view to implement one Click and <Alt>Click start/resume facility. | |||
|- | |- | ||
|16th July to 17th July | |16th July to 17th July | ||