Line 181: |
Line 181: |
| | '''21st June – 27th June''' || Add the automated testing feature to the deployment, testing it and getting feedback from various people. (IRC, Mentors, Mailing Lists and other places) | | | '''21st June – 27th June''' || Add the automated testing feature to the deployment, testing it and getting feedback from various people. (IRC, Mentors, Mailing Lists and other places) |
| |- | | |- |
− | | '''28th June – 3rd July''' || Searching and fixing of bugs. Prepare a report of the project made so far and submitting it for Mid – Term Evaluations | + | | '''28th June – 3rd July''' || Searching and fixing of bugs. Brush up the modules. Prepare a report of the project made so far and submitting it for Mid – Term Evaluations |
| |- | | |- |
| | '''4th July – 11th July''' || Start implementing the features for the “Gallery” part of Web Confusion and create working “Save” and “Share” buttons, testing them and adding them to the deployment. | | | '''4th July – 11th July''' || Start implementing the features for the “Gallery” part of Web Confusion and create working “Save” and “Share” buttons, testing them and adding them to the deployment. |
Line 189: |
Line 189: |
| | '''26th July – 2nd August''' || Testing the complete project, deploying it for the XO and then put a working version of the project for the schools to get a feedback of the problems faced by them. | | | '''26th July – 2nd August''' || Testing the complete project, deploying it for the XO and then put a working version of the project for the schools to get a feedback of the problems faced by them. |
| |- | | |- |
− | | '''3rd August – 15th August''' || Making a list of the feedback and solving the issues priority wise.Cleaning up the UI and wrapping up. | + | | '''3rd August – 15th August''' || Making a list of the feedback and solving the issues priority wise. Cleaning up the UI, sandbox the code, preparing final modules and wrapping up |
| |- | | |- |
| | '''16th August – 28th August''' || Adding finishing touches, making a small guide and a little documentation for making the work for the learner easier. Submitting the project for final evaluation. | | | '''16th August – 28th August''' || Adding finishing touches, making a small guide and a little documentation for making the work for the learner easier. Submitting the project for final evaluation. |