Difference between revisions of "Dextrose/3/Roadmap"

From Sugar Labs
< Dextrose‎ | 3
Jump to navigation Jump to search
m (Tagging as dated)
Line 1: Line 1:
 
Please also look at [[0.94/Roadmap]] and comment if this syncs well with that schedule. FWIW, our Alpha-1 release date corresponds with 0.93.5 hard-code freeze start.
 
Please also look at [[0.94/Roadmap]] and comment if this syncs well with that schedule. FWIW, our Alpha-1 release date corresponds with 0.93.5 hard-code freeze start.
  
 +
{{Dated| To find the most up-to-date roadmap for this dextrose version, please check https://sugardextrose.org/projects/dextrose/wiki/Dextrose_3}}
  
 
{|class="wikitable"
 
{|class="wikitable"

Revision as of 06:41, 13 July 2012

Please also look at 0.94/Roadmap and comment if this syncs well with that schedule. FWIW, our Alpha-1 release date corresponds with 0.93.5 hard-code freeze start.

Warning.png
This page has been marked as important but in need of updating as of May 2016.
See all dated pages
There may be relevant discussion on the talk page.

To find the most up-to-date roadmap for this dextrose version, please check https://sugardextrose.org/projects/dextrose/wiki/Dextrose_3


Target Date Actual Date Release Description/Milestone
08 Aug, 2011 30 Aug, 2011 Alpha-1
  • QA testing starts
22 Aug, 2011 1 Sept, 2011

Major features to be coded to be decided, and captured in bug-trackers. Prioritize features, and bugs and fit them in the development roadmap (by way of wikipages, identifying them as blockers for milestones)

19 Sept, 2011 26 Sept, 2011 Alpha-2
  • All high priority features coded (add bug-id's here)
  • All high priority bugs fixed (add bug-id's here)
  • Review completeness w.r.t. all objectives and features identified in Feature Freeze list
17 Oct, 2011 10 Nov, 2011 Alpha-3
  • All medium priority features coded(add bug-id's here)
  • All medium priority bugs fixed (add bug-id's here) (Alpha-4)
  • All items identified in Feature Freeze coded/fixed. (Alpha-4)
14 Nov 2011
21 Nov 2011
Beta-1
Alpha-4
  • All medium priority bugs fixed (add bug-id's here)
  • All items identified in Feature Freeze coded/fixed.
  • Review overall stability of release.
28 Nov 2011
5 Dec 2011
Beta-2
Beta-1
  • All blocker regressions identified by QA fixed (add bug-id's here).
  • All high and medium priority regressions identified by QA fixed.
12 Dec 2011
19 Dec 2011
Release
  • Final series of meetings | Decide whether we're good enough to release.

Notes

  • Between releases, and atleast until Beta-2, we'll regularly release rpm updates for sugar and other dx related packages. The automated yum updater is supposed to update the releases accordingly.
  • Need to align with testing/QA. Community related emails need to plan around this roadmap.
  • All milestones listed will be communicated atleast via technical release emails on dextrose, sugar-devel, olpc-devel mailing lists.