| + | == Vision == |
| + | Create a users manual for Sugar. |
| + | |
| + | == Road Map == |
| + | Below is a rough draft of a project schedule. |
| + | |
| + | *Week 1 - Target Date July 13. Define scope of document. Assign volunteers to specific tasks. |
| + | *Week 3 - Target Date July 27. Deadline for outlines of chapters to be worked on at sprint. |
| + | *Week 5 - Target Date Aug 17. Conduct sprint. |
| + | |
| + | The rest is based on the chosen release date for the spring release of Sugar. |
| + | |
| + | *Week 0 - Release Final documentation |
| + | *Week -1 Final translation tarballs due |
| + | *Week -4 Documentation freeze |
| + | *Week -5 Book Sprint II |
| + | ... |
| + | Any experienced release manager ready to flesh this out Roadmap. |