| '''Week 1(19th May - 25th May)''' ||  * Begin Coding for the activity
| '''Week 1(19th May - 25th May)''' ||   
* Begin Coding for the activity
* Start making the basic version of the activity according to the decided UI.
* Start making the basic version of the activity according to the decided UI.


|-
|-
| '''Week 2(25th May - 1st June)''' || * Features like Previous/Next Image, Rotation, Resize, crop to be implemented for the basic version.
| '''Week 2(25th May - 1st June)''' ||  
* Features like Previous/Next Image, Rotation, Resize, crop to be implemented for the basic version.
* Both Slideshow ,Time Based SlideShow , save and Converting to thumbnail to be implemented.
* Both Slideshow ,Time Based SlideShow , save and Converting to thumbnail to be implemented.
|-
|-
| '''Week 3(2nd June - 8th June)''' || * Collage creation, compression and Watermark features to be implemented.
| '''Week 3(2nd June - 8th June)''' ||  
* Collage creation, compression and Watermark features to be implemented.
* Basic Version Completed.
* Basic Version Completed.
* Testing the basic version and making it all browser compatible
* Testing the basic version and making it all browser compatible
* '''Deliverable 1'''  
* '''Deliverable 1'''  
|-
|-
| '''Week 4(9th June - 15th June)''' || * Starting with Image Processing and Manipulation.
| '''Week 4(9th June - 15th June)''' ||  
* Starting with Image Processing and Manipulation.
* Integrating CamanJS with the basic version.
* Integrating CamanJS with the basic version.
* Enhancement Functions, plugin system(to create filters) and UI based plugin(drag and drop) to be implemented.
* Enhancement Functions, plugin system(to create filters) and UI based plugin(drag and drop) to be implemented.


|-
|-
| '''Week 5(16th June - 22nd June)''' || * Buffer Week
| '''Week 5(16th June - 22nd June)''' ||  
* Buffer Week
|-
|-
| '''Week 6(23rd June - 29th June)''' ||  
| '''Week 6(23rd June - 29th June)''' ||  
Line 83: Line 88:


|-
|-
| '''Week 8(7th July - 13th July)''' || * Finishing with interactive Pixel mode feature.
| '''Week 8(7th July - 13th July)''' ||  
* Finishing with interactive Pixel mode feature.
* UI based Automatic Version Control.
* UI based Automatic Version Control.


Line 96: Line 102:


|-
|-
| '''Week 11(28th July - 3rd Aug)''' || * Integration Testing and fixing bugs
| '''Week 11(28th July - 3rd Aug)''' ||  
* Integration Testing and fixing bugs
* Documentation
* Documentation


Line 106: Line 113:


|-
|-
| '''Week 13(11th Aug - 17th Aug)''' || * Buffer Week
| '''Week 13(11th Aug - 17th Aug)''' ||  
* Buffer Week
* Finishing Documentation
* Finishing Documentation


|-
|-
| '''17th Aug - 20th Aug'''  || * Final Submission
| '''17th Aug - 20th Aug'''  ||  
* Final Submission
|}
|}