'''Milestone 1'''
 
'''Milestone 1'''
'''May 24 - May 31'''
+
 
 +
'''May 24 - May 31 : '''
 
Work on connection manager to provide : Unicast, Broadcast, Multicast of messages and also to make the activity shareable.  
 
Work on connection manager to provide : Unicast, Broadcast, Multicast of messages and also to make the activity shareable.  
   −
'''June 1 - June 9'''
+
'''June 1 - June 9 : '''
 
Work on the viewer to enable display of question/slides, facility to mark/type answers/comments according to the UI Specs generated in the Community Bonding period.  
 
Work on the viewer to enable display of question/slides, facility to mark/type answers/comments according to the UI Specs generated in the Community Bonding period.  
   −
'''June 9 - June 12'''
+
'''June 9 - June 12 : '''
 
Make an AnswerSheetCollector and Marker Module.  
 
Make an AnswerSheetCollector and Marker Module.  
   −
'''June 12 - June 18'''
+
'''June 12 - June 18 : '''
 
Testing and feedback cycle for MileStone 1
 
Testing and feedback cycle for MileStone 1
    
'''Milestone 2'''
 
'''Milestone 2'''
'''June 19 - June 25'''
+
 
 +
'''June 19 - June 25 : '''
 
Make the interface for Demo Mode at the controller side. The Demo Mode should work seamlessly by June 25.  
 
Make the interface for Demo Mode at the controller side. The Demo Mode should work seamlessly by June 25.  
   −
'''June 26 - July 6'''
+
'''June 26 - July 6 : '''
 
Make the Editor for making Questions/Slides.  
 
Make the Editor for making Questions/Slides.  
   −
'''July 6 - July 12'''
+
'''July 6 - July 12 : '''
 
Provide a way to overlay comments/answers over original questions/slides.  
 
Provide a way to overlay comments/answers over original questions/slides.  
   −
'''July 13'''
+
'''July 13 : '''
 
Fill up mid-term evaluation.  
 
Fill up mid-term evaluation.  
   −
'''July 13 - July 20'''
+
'''July 13 - July 20 : '''
 
Testing and Feedback cycle for MileStone 2
 
Testing and Feedback cycle for MileStone 2
    
'''Milestone 3'''
 
'''Milestone 3'''
'''July 21 - July 28'''
+
 
 +
'''July 21 - July 28 : '''
 
Work on making a database for questions and answers to be put up on a school server.  
 
Work on making a database for questions and answers to be put up on a school server.  
   −
'''July 29 - August 5'''
+
'''July 29 - August 5 : '''
 
Work on documentation and provide a nice website for the activity where people can put up questions and answers.  
 
Work on documentation and provide a nice website for the activity where people can put up questions and answers.  
   −
'''August 5 - August 10'''
+
'''August 5 - August 10 : '''
 
Port the activity on Windows also.  
 
Port the activity on Windows also.  
   −
'''August 10 - August 17'''
+
'''August 10 - August 17 : '''
 
Internal Alpha release cycle.  
 
Internal Alpha release cycle.  
   −
'''August 17 - August 23'''
+
'''August 17 - August 23 : '''
 
Feedback incorporation.  
 
Feedback incorporation.  
   −
'''August 24'''
+
'''August 24 : '''
 
Final Evaluation
 
Final Evaluation
   −
'''August 25 - later'''
+
'''August 25 - later : '''
 
Alpha Release. This will be for a period of 1 month. After this a beta release of a period of 2 months. After this I will try to push it to be a part of the official distributed activties in Sugar.  
 
Alpha Release. This will be for a period of 1 month. After this a beta release of a period of 2 months. After this I will try to push it to be a part of the official distributed activties in Sugar.  
 
----
 
----
50