Changes

Jump to navigation Jump to search
no edit summary
Line 62: Line 62:  
| 22nd July - 29th July<br>(Week 10) || '''Buffer Week 2'''
 
| 22nd July - 29th July<br>(Week 10) || '''Buffer Week 2'''
 
|-
 
|-
| 29th July - 5th July<br>(Week 11) || Start updating the Testing Guide of the activities on docs.sugarlabs.org  
+
| 29th July - 5th August<br>(Week 11) || Start updating the Testing Guide of the activities on docs.sugarlabs.org  
 
|-
 
|-
| 5th July - 12th July<br>(Week 12)  || Expected Pencil Down Date
+
| 5th August - 12th August<br>(Week 12)  || Expected Pencil Down Date
 
|-
 
|-
| 12th July - 19th July<br>(Week 13)  || Polish up the tests, and manage the wiki page of the project and compile the content
+
| 12th August - 19th August<br>(Week 13)  || Polish up the tests, and manage the wiki page of the project and compile the content
 
|-
 
|-
| 19th July - 26th July<br>(Week 14)  || Firm Pencil Down & Final Evaluations
+
| 19th August - 26th August<br>(Week 14)  || Firm Pencil Down & Final Evaluations
 
|}
 
|}
  
13

edits

Navigation menu