| 17th June - 24th June - (Week 5) || Tests for Browse and start working on the initial tests for TurtleArt  
 
| 17th June - 24th June - (Week 5) || Tests for Browse and start working on the initial tests for TurtleArt  
 
|-
 
|-
| 24th June - 1st July - (Week 6) || Mid-Term Evaluations - '''Buffer Week'''
+
| 24th June - 1st July - (Week 6) || Mid-Term Evaluations - Tests for TurtleArt and finish up any remaining work from preceding weeks
 
|-
 
|-
 
| 1st July - 8th July - (Week 7) || Tests for TaBasic, TaBlock, TaCanvas
 
| 1st July - 8th July - (Week 7) || Tests for TaBasic, TaBlock, TaCanvas
Line 59: Line 59:  
| 15th July - 22nd July - (Week 9) || Finish up Turtle Art and Start working on Pippy
 
| 15th July - 22nd July - (Week 9) || Finish up Turtle Art and Start working on Pippy
 
|-
 
|-
| 22nd July - 29th July - (Week 10) || Buffer
+
| 22nd July - 29th July - (Week 10) || Buffer - Start with Tests for Pippy
 
|-
 
|-
 
| 29th July - 5th August - (Week 11) || Tests for Pippy
 
| 29th July - 5th August - (Week 11) || Tests for Pippy