| '''Week 1(19th May - 25th May)''' ||  * Begin Coding for the activity
+
| '''Week 1(19th May - 25th May)''' ||   
 +
* Begin Coding for the activity
 
* Start making the basic version of the activity according to the decided UI.
 
* Start making the basic version of the activity according to the decided UI.
    
|-
 
|-
| '''Week 2(25th May - 1st June)''' || * Features like Previous/Next Image, Rotation, Resize, crop to be implemented for the basic version.
+
| '''Week 2(25th May - 1st June)''' ||  
 +
* Features like Previous/Next Image, Rotation, Resize, crop to be implemented for the basic version.
 
* Both Slideshow ,Time Based SlideShow , save and Converting to thumbnail to be implemented.
 
* Both Slideshow ,Time Based SlideShow , save and Converting to thumbnail to be implemented.
 
|-
 
|-
| '''Week 3(2nd June - 8th June)''' || * Collage creation, compression and Watermark features to be implemented.
+
| '''Week 3(2nd June - 8th June)''' ||  
 +
* Collage creation, compression and Watermark features to be implemented.
 
* Basic Version Completed.
 
* Basic Version Completed.
 
* Testing the basic version and making it all browser compatible
 
* Testing the basic version and making it all browser compatible
 
* '''Deliverable 1'''  
 
* '''Deliverable 1'''  
 
|-
 
|-
| '''Week 4(9th June - 15th June)''' || * Starting with Image Processing and Manipulation.
+
| '''Week 4(9th June - 15th June)''' ||  
 +
* Starting with Image Processing and Manipulation.
 
* Integrating CamanJS with the basic version.
 
* Integrating CamanJS with the basic version.
 
* Enhancement Functions, plugin system(to create filters) and UI based plugin(drag and drop) to be implemented.
 
* Enhancement Functions, plugin system(to create filters) and UI based plugin(drag and drop) to be implemented.
    
|-
 
|-
| '''Week 5(16th June - 22nd June)''' || * Buffer Week
+
| '''Week 5(16th June - 22nd June)''' ||  
 +
* Buffer Week
 
|-
 
|-
 
| '''Week 6(23rd June - 29th June)''' ||  
 
| '''Week 6(23rd June - 29th June)''' ||  
Line 83: Line 88:     
|-
 
|-
| '''Week 8(7th July - 13th July)''' || * Finishing with interactive Pixel mode feature.
+
| '''Week 8(7th July - 13th July)''' ||  
 +
* Finishing with interactive Pixel mode feature.
 
* UI based Automatic Version Control.
 
* UI based Automatic Version Control.
   Line 96: Line 102:     
|-
 
|-
| '''Week 11(28th July - 3rd Aug)''' || * Integration Testing and fixing bugs
+
| '''Week 11(28th July - 3rd Aug)''' ||  
 +
* Integration Testing and fixing bugs
 
* Documentation
 
* Documentation
   Line 106: Line 113:     
|-
 
|-
| '''Week 13(11th Aug - 17th Aug)''' || * Buffer Week
+
| '''Week 13(11th Aug - 17th Aug)''' ||  
 +
* Buffer Week
 
* Finishing Documentation
 
* Finishing Documentation
    
|-
 
|-
| '''17th Aug - 20th Aug'''  || * Final Submission
+
| '''17th Aug - 20th Aug'''  ||  
 +
* Final Submission
 
|}
 
|}
  