Changes

Jump to navigation Jump to search
no edit summary
Line 1: Line 1:  
'''<big><big>About you</big></big>'''<br><br>
 
'''<big><big>About you</big></big>'''<br><br>
 
'''What is your name?'''<br>
 
'''What is your name?'''<br>
My name is Gaurav Parida, and I am a 2nd year undergraduate student at [http://www.iiit.ac.in/ International Institute of Technology (IIIT), Hyderabad].
+
My name is Gaurav Parida, and I am a 2nd year undergraduate student at [http://www.iiit.ac.in/ International Institute of Information Technology (IIIT), Hyderabad].
 
<br><br>
 
<br><br>
 
'''What is your email address?'''<br>
 
'''What is your email address?'''<br>
Line 58: Line 58:  
| 8th July - 15th July<br>(Week 8) || '''Buffer Week 1'''
 
| 8th July - 15th July<br>(Week 8) || '''Buffer Week 1'''
 
|-
 
|-
| 15th July - 22nd July<br>(Week 9) || Write tests for Etoys
+
| 15th July - 22nd July<br>(Week 9) || Write tests for TurtleArt
 
|-
 
|-
 
| 22nd July - 29th July<br>(Week 10) || '''Buffer Week 2'''
 
| 22nd July - 29th July<br>(Week 10) || '''Buffer Week 2'''
 
|-
 
|-
| 29th July - 5th July<br>(Week 11) || Start updating the Testing Guide of the activities on docs.sugarlabs.org  
+
| 29th July - 5th August<br>(Week 11) || Start updating the Testing Guide of the activities on docs.sugarlabs.org  
 
|-
 
|-
| 5th July - 12th July<br>(Week 12)  || Expected Pencil Down Date
+
| 5th August - 12th August<br>(Week 12)  || Expected Pencil Down Date
 
|-
 
|-
| 12th July - 19th July<br>(Week 13)  || Polish up the tests, and manage the wiki page of the project and compile the content
+
| 12th August - 19th August<br>(Week 13)  || Polish up the tests, and manage the wiki page of the project and compile the content
 
|-
 
|-
| 19th July - 26th July<br>(Week 14)  || Firm Pencil Down & Final Evaluations
+
| 19th August - 26th August<br>(Week 14)  || Firm Pencil Down & Final Evaluations
 
|}
 
|}
  
13

edits

Navigation menu