Our [http://groups.google.com/group/xotoaster/browse_thread/thread/f9b9898056f6949d approval] included an estimated schedule.  This page is to be updated as progress is completed and the schedule changes.
 
Our [http://groups.google.com/group/xotoaster/browse_thread/thread/f9b9898056f6949d approval] included an estimated schedule.  This page is to be updated as progress is completed and the schedule changes.
  
* Begin - Approval April 18, 2010
+
* Current Schedule
** Update - June 7, 2010 - Meeting with Alex, Sameer and Grant
+
** Begin - Approval April 18, 2010
** Update - June 11, 2010 - minimum Activity installs and runs
+
*** Update - June 7, 2010 - Meeting with Alex, Sameer and Grant
* Month 3, July 18, 2010 - produce a minimum UI to replicate command line features for CD burning and baseline USB Stick functionality
+
*** Update - June 11, 2010 - minimum Activity installs and runs
* Month 5, Sept 18, 2010 - Test, test, test, adapt to different XO images.
+
** Month 6 - [http://www.olpcsf.org/CommunitySummit2010/ Community Summit 2010]
* Month 6, Oct 18, 2010 - Announce and gather further feedback.
+
 
* Month 9, Jan 18, 2011 - collect feedback and incorporate into bug fixes and new feature plans.
+
 
* Month 12, Aptil 18, 2011 - support, gather feedback, develop & fix, iterate.
+
 
 +
* Original Schedule
 +
** Begin - Approval April 18, 2010
 +
** Month 3, July 18, 2010 - produce a minimum UI to replicate command line features for CD burning and baseline USB Stick functionality
 +
** Month 5, Sept 18, 2010 - Test, test, test, adapt to different XO images.
 +
** Month 6, Oct 18, 2010 - Announce and gather further feedback.
 +
** Month 9, Jan 18, 2011 - collect feedback and incorporate into bug fixes and new feature plans.
 +
** Month 12, Aptil 18, 2011 - support, gather feedback, develop & fix, iterate.

Latest revision as of 13:20, 23 October 2010

Our approval included an estimated schedule. This page is to be updated as progress is completed and the schedule changes.

  • Current Schedule
    • Begin - Approval April 18, 2010
      • Update - June 7, 2010 - Meeting with Alex, Sameer and Grant
      • Update - June 11, 2010 - minimum Activity installs and runs
    • Month 6 - Community Summit 2010


  • Original Schedule
    • Begin - Approval April 18, 2010
    • Month 3, July 18, 2010 - produce a minimum UI to replicate command line features for CD burning and baseline USB Stick functionality
    • Month 5, Sept 18, 2010 - Test, test, test, adapt to different XO images.
    • Month 6, Oct 18, 2010 - Announce and gather further feedback.
    • Month 9, Jan 18, 2011 - collect feedback and incorporate into bug fixes and new feature plans.
    • Month 12, Aptil 18, 2011 - support, gather feedback, develop & fix, iterate.