Difference between revisions of "Activities/Toaster/Schedule"
< Activities | Toaster
Jump to navigation
Jump to search
m (installs and runs) |
(summit update) |
||
Line 1: | Line 1: | ||
Our [http://groups.google.com/group/xotoaster/browse_thread/thread/f9b9898056f6949d approval] included an estimated schedule. This page is to be updated as progress is completed and the schedule changes. | Our [http://groups.google.com/group/xotoaster/browse_thread/thread/f9b9898056f6949d approval] included an estimated schedule. This page is to be updated as progress is completed and the schedule changes. | ||
− | * Begin - Approval April 18, 2010 | + | * Current Schedule |
− | ** Update - June 7, 2010 - Meeting with Alex, Sameer and Grant | + | ** Begin - Approval April 18, 2010 |
− | ** Update - June 11, 2010 - minimum Activity installs and runs | + | *** Update - June 7, 2010 - Meeting with Alex, Sameer and Grant |
− | * Month 3, July 18, 2010 - produce a minimum UI to replicate command line features for CD burning and baseline USB Stick functionality | + | *** Update - June 11, 2010 - minimum Activity installs and runs |
− | * Month 5, Sept 18, 2010 - Test, test, test, adapt to different XO images. | + | ** Month 6 - [http://www.olpcsf.org/CommunitySummit2010/ Community Summit 2010] |
− | * Month 6, Oct 18, 2010 - Announce and gather further feedback. | + | |
− | * Month 9, Jan 18, 2011 - collect feedback and incorporate into bug fixes and new feature plans. | + | |
− | * Month 12, Aptil 18, 2011 - support, gather feedback, develop & fix, iterate. | + | |
+ | * Original Schedule | ||
+ | ** Begin - Approval April 18, 2010 | ||
+ | ** Month 3, July 18, 2010 - produce a minimum UI to replicate command line features for CD burning and baseline USB Stick functionality | ||
+ | ** Month 5, Sept 18, 2010 - Test, test, test, adapt to different XO images. | ||
+ | ** Month 6, Oct 18, 2010 - Announce and gather further feedback. | ||
+ | ** Month 9, Jan 18, 2011 - collect feedback and incorporate into bug fixes and new feature plans. | ||
+ | ** Month 12, Aptil 18, 2011 - support, gather feedback, develop & fix, iterate. |
Latest revision as of 13:20, 23 October 2010
Our approval included an estimated schedule. This page is to be updated as progress is completed and the schedule changes.
- Current Schedule
- Begin - Approval April 18, 2010
- Update - June 7, 2010 - Meeting with Alex, Sameer and Grant
- Update - June 11, 2010 - minimum Activity installs and runs
- Month 6 - Community Summit 2010
- Begin - Approval April 18, 2010
- Original Schedule
- Begin - Approval April 18, 2010
- Month 3, July 18, 2010 - produce a minimum UI to replicate command line features for CD burning and baseline USB Stick functionality
- Month 5, Sept 18, 2010 - Test, test, test, adapt to different XO images.
- Month 6, Oct 18, 2010 - Announce and gather further feedback.
- Month 9, Jan 18, 2011 - collect feedback and incorporate into bug fixes and new feature plans.
- Month 12, Aptil 18, 2011 - support, gather feedback, develop & fix, iterate.